Completed project

project details:

Project: Data Center

Location: Jebal Ali Group LLC

Client: Al Tayer Group LLC

Sector: Industrial

Start Date: June 2016

Completion Date: October 2016

 

overview:

This Data Center facility is to be constructed on the Al Khaleej site located in Jebal Ali Industrial 1.This new RC Frame G+1 Building will house a Data Centre for the Al Tayer Stocks Retail division as part of the new NEO Omni Channel Vision. Substructure is of typical RC Pad footings with tie beams and Ground Floor slab.

 

External envelope is in Insulated Blockwork finished with painted render. Roof covering is a built up system finished with a waterproof membrane and plinth supports for the roof mounted mechanical plant.

 

Adjacent to the Data Centre building will be a new Generator building housing 3 number 500KVA Generators providing 24/7 failsafe back up to the mains power supply.

 

Internal finishes are Metal Stud partitioning, Raised access floors and painted walls.

 

New Building Services (MEP) provided throughout and will be undertaken by the ATS MEP Division.

 

Project Management: Al Tayer Projects Dept.

 

AOR & Design Services by : ART Consultants

 

Cost Consulting : Al Tayer Projects Dept.

 

project data:

  • 2 Story Building
  • Reinforced Concrete Frame
  • Total floor area 1200m²
  • External Painted Render Facade
  • Provision for 1 Nr. Lift
  • Ground Floor – For Future Development
  • 1st Floor, Data Centre, Server Rooms